How Much Will my Foundations Cost?


 

By David Snell

Foundations are the one element of a construction project that it is impossible to fully plan out until you start on site (as ground conditions and requirements vary), meaning budgeting this section of your build will be, at best, general. Most builders quote, without further information or instruction, on the basis of what is known as a deep strip foundation. This assumes a trench 600mm wide and 1,200mm deep for all external walls, and internal load-bearing walls with a minimum 225mm of concrete tamped level.

But, of course, even this simple standard assumes a dead level site and makes no provision for the disposal or dispersal of the excavated spoil. (On this note, you can save money by redistributing spoil on site for landscaping purposes.) As soon as you have a site with a slope, then steps have to be created in the concrete, and that means shuttering up in order to maintain the level surface of the concrete.

Although concrete is expensive, many decide from the outset to swap to a 'trenchfill' foundation, whereby the excavations are filled to within 200mm of the ground level. It means much more concrete but it gets you out of the ground in one day and negates the need for bricklayers and clocks below ground level. In unstable or wet conditions, that can be a real bonus and, in the end, the costs aren't much more.

The presence of trees, especially where the subsoil is clay, will crank up the requirements even further, with the possibility that trenches will have to be up to 3m deep. This is because trees affect the moisture content of the soil at lower depths and the fact that some clay soils expand or contract according to their moisture content.

It is quite common for there to be a requirement for one or both sides of the trench to be lined with compressible material and for a slip membrane to be introduced. This may, therefore, necessitate a wider digger bucket being used.

Comparing Foundations Costs

The following provides an indication of costs for a 7x10m building with one internal cross wall (and including labour, plant and materials), varied by foundation type:

Deep Strip Foundations

Excavate 30m3

 £812.80

Bulked up to 45m3 loaded into lorries

 £685.19
 Soil disposal incl tipping charges  £1,125.00
 Reinforcement mesh  £192.00
 Concrete foundations 10m3  £1,339.45
 Total   £4,154.44

 Trench Foundations

Excavate 30m3 £812.80
Bulked up 45m3 loaded into lorries £685.19
Soil disposal incl tipping charges £1,125.00
Reinforcement mesh £384.00
Concrete foundations 25m3 £3,349.64
Total £6,356.63

2m-deep Trenchfill Foundations

Excavate 50m3 £1,500.00
Bulked up 75m3 loaded into lorries £1,141.99
Soil disposal incl tipping charges £1,875.00
Compressible material, slip membrane and positioning £606.00
Reinforcement mesh £408.00
Concrete foundations 45m3 £6,029.35
Total  £11,560.34

(NB: With the costs for a pile and ringbeam system for a building such as this, running at £8,000-£12,000, it can pay to swap to such a system from a dug foundation.)